At approximately 15:30 PST we lost power to all equipment hosted in our Costa Mesa facility. This power failure is localized to specific cabinets at the facility and is not building wide. We are working with engineers to resolve this issue as soon as possible.

This post will be updated with the latest developments. Please check back here for updates.

UPDATE 17:00 – We have been informed by the building engineers that power should be restored within the hour.

UPDATE 18:45 – Power has been restored to all equipment in the Costa Mesa data center. A faulty A/C unit caused a number of breakers to heat up and fail. Currently all servers are online and operational.